More & more – PROGRESS!!! Installing the galloway and construction of the headframe.

This picture of the galloway installed in the subcollar was taken on December 13, 2012 by Robert McKnight, Nevada Copper Corporation, Executive Vice President

1st tier of the headframe

The Galloway is now installed into the shaft and will have 3 decks (walkways).

This is the first tier of structural steel in place for the headframe and is 53 feet high. The second tier will be approximately 60 feet and the third tier will be approximately 40 ft.